Timeline

Progress You Can Track

The Casino Project has been more than a decade in the making. Below is a snapshot of key milestones and what’s ahead.
2006–2015: Laying the Groundwork
  • 2006: 
    • Western Copper acquires the Casino Project and establishes Casino Mining Corporation
  • 2008–2015: 
    • Initial environmental and baseline studies begin
    • Early-stage engagement with First Nations and community stakeholders
    • Field work begins on water, wildlife, and archaeological research
    • Initial Project Proposal for the Casino Project  submitted to the Yukon Environmental and Socio-economic Assessment Board
W3_2021-08-10_DN_21Y0133
2016–2020: Assessment Path Chosen
  • 2016-2018: 
    • YESAB refers the Casino Project to a YESAB Panel Review — the first ever in Yukon
    • YESAB issues initial ESE Statement Guidelines
    • Casino Mining launches the Best Available Tailings Technology (BATT) Study, with participation from: Yukon First Nations, YESAB, Yukon Government, Independent Engineering Review Panel (IERP)
    • Study evaluates nearly 500 different options for the safe and secure storage of mine waste and tailings
    • Preferred design selected to maximize safety and environmental protection
4
2019–2021: Resource Growth & Strategic Investments
  • 2019–2021
    • Carmacks Bypass contract awarded: The first 8 km of the all-weather access corridor.
    • Exploration success: Successive drill campaigns extend the Casino deposit well beyond the 2012 reserve limits.
    • Resource update: New data drives significant resource expansion, feeding into an updated Preliminary Economic Assessment.
    • Rio Tinto backs Casino: Strategic equity investment; appoints a member to the Casino Technical & Sustainability Committee.
CarmacksBridge
2021–2023: Technical Reports & Access Improvements
  • 2022: 
    • Casino publishes updated Feasibility Study, refining: Site infrastructure, Tailings storage, Waste and water management, Power generation
  • 2023: 
    • Release of updated MNP Economic Impacts Report, projecting: $11.2B in government revenues, $1.3B annually to Yukon’s economy
  • 2023: 
    • Completion of the Carmacks Bypass Project, the first section of the proposed access road
    • Strategic investment from Mitsubishi Materials; appoints a member to the Casino Technical & Sustainability Committee
RRCAGM3
2022–2025: Preparing for Submission
  • Ongoing engagement with Yukon First Nations
  • Continued Traditional Knowledge integration
  • Refinement of the Environmental and Socio-Economic Effects (ESE) Statement
  • Target submission of the ESE Statement to YESAB: Summer 2025
2

What Comes Next?

After the ESE Statement is submitted, and if YESAB accepts the filing, the appointed Panel will:

  • Conduct a technical review
  • Ask for additional information if it is needed
  • Host public hearings
  • Deliver a final Panel Report and Recommendations

Once Decision Bodies review and approve the recommendations, the Casino Project can move forward with final permitting, including:

  • Quartz Mining Licence
  • Water Use Licence

Stay Informed

Subscribe to receive project updates, event invitations, and important announcements — delivered straight to your inbox.

Helpful Resources

We’ve pulled together the most relevant documents so you can download and explore at your own pace.